Waterline Replacement- Phase 2
The waterline replacement includes approximately 5,000 linear feet of 8-inch waterline. The plans were approved by Harris County and Harris County Flood Control in the summer of 2023. The plans were bid and awarded in an amount of $554,978.00 to Bull-G Construction. The construction project is expected to begin on June 28, 2024. Phase 2 should be completed by winter of 2024. Phase 2 includes the following streets:
– Wade Road
– Johnson Road
– Juarez Street
– Morelos Road